Bus depot retrofit

Ezhou Bus Depot Platform Integration Retrofit

Twenty-two 120 kW DC chargers were upgraded and integrated into a unified energy platform while retaining the main equipment.

CategoryCharger retrofit caseCustomer typeBus charging depotLocationEzhou, Hubei, ChinaContent noteBased on company project information and site images
22 × 120 kW DC chargers 2,640 kW installed capacity Five-day field transition
Ezhou Bus Depot Platform Integration Retrofit project image
01

Background

The depot required centralised equipment and operating information while retaining its existing charger assets.

02

Implementation

Communication adaptation and critical control upgrades were completed in batches, followed by start, charge, stop and data-reporting checks.

03

Outcome

The depot can centrally view charging records and equipment status to support vehicle charging schedules and ongoing maintenance.